Outline vs full planning permission explained

12/06/2026

Uncategorized

Outline vs full planning permission explained

Outline planning permission settles the principle of a development; full planning permission settles the detail. Outline leaves the specifics to be agreed later, while full permission approves the complete, detailed scheme in one go.

This guide covers England; the other UK nations run comparable but separate systems.

What is outline planning permission?

Outline planning permission establishes whether the principle of a proposed development is acceptable, leaving the details to be agreed later through reserved matters.

Outline permission is often used to test the principle before you commit to detailed design costs. If you’re not certain a site will be accepted, an outline application establishes that before you invest in detailed drawings.

It is also used to sell land with the principle of development established, which makes a site far more attractive and valuable to a buyer.

You apply to the local planning authority (LPA), the council body that decides planning applications. Our guide to planning applications covers how the application process works.

What is full planning permission?

Full planning permission approves the complete, detailed proposal in a single application. Once it is granted, subject to any conditions, you can begin the development. The design, layout, appearance and access are all decided at once, and there is no second stage.

Most householder projects go straight for full permission. If you’re building an extension or putting up a single new home you intend to build yourself, there is usually no reason to split the decision in two. Our guides to extensions and planning applications cover the householder route.

What are reserved matters?

Reserved matters are the details left for later approval after an outline permission is granted. There are five in total, and an outline permission typically defers some or all of them:

Once outline permission is in place, you submit a reserved-matters application to get these details approved.

Because the outline permission has already settled the principle of the development, the reserved-matters application deals only with the specifics, assessed against what the outline permission established.

If you are unsure which matters the council will determine should be reserved or settled up front, our pre-application advice page explains how to scope the right approach with the authority.

  • Layout – how the buildings, routes and spaces are arranged on the site.
  • Scale – the height, width and length of the building.
  • Appearance – the look of the development, including materials.
  • Access – how you get to and move through the site (this is however quite often settled at the outline stage).
  • Landscaping – the treatment of the open parts of the site.

Outline vs full planning permission: which do you need?

Choose outline permission to establish the principle before you commit to detailed design costs. Choose full permission when you want to build now, or when the design itself is central to the scheme.

Outline tends to suit: – Larger or speculative sites where you want to confirm if planning will be accepted in principle before committing to the full detailed design. – Selling land, where an established principle or outline planning consent adds value. – Testing a difficult or uncertain site before spending on detailed drawings.

Full permission tends to suit: – Householder work – extensions, conversions and single homes you plan to build. – Any project where you want a permission you can commence with straight away. – Design-led schemes, where the quality of the design is central to winning approval.

For a design-led home or extension, a full application is usually the better route. Outline permission cannot really capture what makes a bespoke design work, so that quality needs to be in front of the planning officer from the start.

That is true of a countryside home under HO11, previously known as Paragraph 84, of a new dwelling or self-build, and of a design-led extension. We’ll give you an honest steer on the right route for your project.

How long does outline planning permission last?

Under the Town and Country Planning Act 1990, reserved matters must be submitted within three years of outline permission being granted, and in England the development must then begin within two years of the final reserved-matters approval, unless the local planning authority sets different periods in the permission. Miss those deadlines and the permission can lapse.

The later reserved-matters application adds its own assessment period on top of the outline decision. Outline can spread the cost across two stages, but it does not necessarily reach a buildable position any faster than a full application. It is often slower.

Planning time limits are set in legislation and can change, so treat these periods as current-at-writing and check the position before you rely on them.

How much does outline planning permission cost?

There is a statutory planning application fee set by government that varies with the development, in terms of the site’s size and the scale of development, plus professional fees for the drawings and reports the application needs. Outline planning can cost less up front than a full application, because you’re not paying for a complete detailed design yet, but it adds the later reserved-matters application, with its own fee and professional costs.

So the total is not necessarily lower, just split across two stages.

Frequently asked questions

What is outline planning permission?

Outline planning permission establishes whether the principle of a development is acceptable, leaving the details, the reserved matters, to be approved later. It lets you confirm a site can be built on before committing to a full, detailed design, and it is often used to sell land with the principle of development established.

What is the difference between outline and full planning permission?

Outline permission settles the principle of the development and leaves the detail to a later reserved-matters application. Full permission decides the whole scheme, including the detail, in one application, and once granted lets you begin the development, subject to conditions.

What are reserved matters?

Reserved matters are the details left for later approval after an outline permission is granted: layout, scale, appearance, access and landscaping. You submit a reserved-matters application to get them approved, assessed against the principle the outline permission already established.

How long does outline planning permission last?

Under the Town and Country Planning Act 1990, reserved matters must be submitted within three years of the outline permission being granted, and in England the development must then begin within two years of the final reserved-matters approval, unless the local planning authority sets different periods in the permission. Miss these deadlines and the permission can lapse. Time limits are set in legislation and can change, so check the current position before relying on them.

Can you sell land with outline planning permission?

Yes, and it is one of the main reasons people use it. An outline permission establishes that the site can be developed in principle, which makes it more attractive and more valuable to a buyer, who then handles the reserved-matters detail.

Do I need an architect for outline planning permission?

An outline application needs drawings and supporting information, and the quality of that material affects the outcome. An architect prepares those drawings and, on a design-led scheme, sets the design direction from the start.

How much does outline planning permission cost?

There is a statutory planning application fee set by government that varies with the development, in terms of the site’s size and the scale of development, plus professional fees for drawings and reports. Outline planning can cost less up front than a full application, but it adds a later reserved-matters application with its own costs, so the total is split across two stages rather than necessarily lower.

Share on your socials...

Facebook X LinkedIn

Let’s create something Amazing

We believe that architecture is not just about buildings, it’s about building relationships grounded in trust, transparency, and shared vision.

With over two decades of comprehensive experience in the architecture sector, our service offering is broad, meticulous, and finely tuned.

Let’s create something Amazing

Get started today...

It all starts here, tell us a bit about your project and one of our expert architects will get in touch to discuss your idea in more detail.